Renovating Property in Yerevan: A Practical Guide for 2026

May 12, 2026

01Introduction. Who this guide is for

This guide is for anyone who:

  • is considering renovating an apartment or house in Armenia for themselves;
  • is preparing a property for rent or sale.

Our goal is to help you go through this process “without surprises”: to understand the order of actions, current prices, risks and related costs.

The guide was compiled by the “Meters in Drams” community together with specialists from the renovation and construction field. After studying it fully, you will be able to organize a renovation on your own, from the idea to the finished result, or at the very least understand the subject much better and avoid costly mistakes when working with contractors.

If you have questions, you can get a consultation in our channel: https://t.me/sqm_am

02The renovation market at the start of 2026

The situation on Yerevan’s renovation market is largely shaped by the delayed effect of previous years. Until the end of 2024 an income tax refund program was in effect, which stimulated active purchases of new builds. In 2025 the program ended, and demand for buying apartments dropped noticeably.

However, the renovation market lives with a delay: apartments bought in 2022–2024 are being commissioned and handed over to owners en masse right now. As a result, despite the decline in new deals, the volume of renovations in Yerevan continues to grow. New square meters enter the market faster than the number of qualified crews and specialists grows.

This creates a structural imbalance: there are more properties, but the number of contractors doesn’t grow proportionally. That leads to a labor shortage on the renovation market, longer timelines and rising prices for quality services. Finding a strong and responsible team gets harder, and mistakes in choosing a contractor get more expensive.

What this means:

  • demand for renovation is high;
  • good crews are in short supply;
  • timelines stretch;
  • prices for quality work are rising.

Conclusion: the main risk is hiring mediocre contractors and losing time, energy and money on rework.

03Specifics of renovation in Armenia

Renovation in Armenia has its own specifics. It’s best to account for them in advance: some show up at the stage of buying the apartment, some when looking for craftsmen, and some during the construction itself.

Shell finish

The first thing a new-build buyer most often faces is the absence of a finished interior from the developer. Most new apartments in Armenia are sold as an “empty box”: walls, a concrete floor, basic utility outlets, and everything else you have to do yourself.

That’s why a full renovation budget almost always needs to be added to the apartment’s price right away. Otherwise you can buy a property at a comfortable price and then discover that bringing it to a livable state is a separate large project that significantly increases the total cost of the purchase.

Hidden scope of work

Another common story, usually with resale: at the start the renovation seems simple, and then it starts to grow. For example, you planned a cosmetic update: paint the walls, replace the floor and update the lighting. Then it turns out the wiring is old, the pipes need replacing, the ventilation works poorly, and the walls need to be fully leveled rather than just repainted.

As a result, a small renovation turns into a major one. That’s why before starting work it’s important to check the apartment’s condition: electrics, plumbing, ventilation, walls, floors and hidden utilities. This helps you understand the real scope of work in advance, rather than discovering it in an already dismantled apartment.

Ideally, do this even before buying the apartment. For example, as part of our resale apartment selection, we invite an engineer before the purchase who inspects the apartment and provides a detailed checklist. It lets you avoid buying a “pig in a poke” by clearly understanding how much more you will have to invest.

Material prices

The next important point is materials. Many construction and finishing items are imported into Armenia, so prices can be higher than expected, and warehouse availability can change from week to week. This especially applies to tiles, plumbing, lighting, fittings, appliances, doors and made-to-order materials. If something is critical for the project, it’s better to check availability in advance and build a budget reserve.

Finding craftsmen through recommendations

When it comes to choosing contractors, many people look for craftsmen “through their own people”. In Armenia this really is one of the most effective methods: a personal recommendation often means more than attractive advertising. But a recommendation doesn’t replace checking. It’s still worth looking at the craftsman’s real work, discussing terms, understanding their approach, and agreeing in advance on cost, timelines and payment procedure.

Lack of common standards

Many private craftsmen and crews work on the market, but there is often no unified approach to quality, technology and organization of work. One craftsman works neatly and by the book, another “the way he’s used to”, a third however it turns out. So the result of a renovation depends very much on the specific people: their experience, responsibility, care and willingness to communicate properly with the client.

Working without contracts

Many people still make verbal agreements. It seems fast and convenient, especially if the craftsman came by recommendation. But in a dispute you have almost nothing to rely on: it’s hard to prove what exactly was promised, by when, for how much money and of what quality.

04The order of work: where to start

The main mistakes at the start:

  • Renovating without a project. This is the root of most problems. No plan leads to constant rework, conflicts with craftsmen and missed deadlines.
  • No estimate. If the budget is calculated only “in your head”, it will almost certainly blow up during the work. An estimate is needed to see the real scale of the renovation in advance.
  • No professional assessment of the property and its utility systems. For example, you planned to just paint the walls and replace the floor, and during the work it turned out that all the wiring has to be replaced. That’s how a small renovation turns into a major one.
  • Hiring the cheapest craftsmen. Choosing a contractor by price alone and then paying a second time to fix the screw-ups. It’s better to look not only at cost but also at experience, approach and the quality of past work.

As you can see, most renovation problems arise not during the work, but before it starts, because of wrong expectations, weak planning and chaos in the process. That’s why the main decisions must be made before work begins.

Step-by-step renovation order

  1. 1Define the purpose and level of the renovation (budget, comfort, premium).
  2. 2Find a designer and create a design project. The designer helps define the style, think through the layout and living scenarios, and prepare technical drawings for the builders.
  3. 3Review the project and get a visualization. Before the renovation it’s important to go through the project once more, make corrections and see the future interior in advance.
  4. 4Select materials, furniture, lighting and plumbing. This is usually done together with the designer.
  5. 5Choose a contractor and sign a contract. The contract helps fix the cost, timelines, payment stages and responsibilities of the parties.
  6. 6Organize purchasing and delivery of materials. Supply delays often stop a renovation.
  7. 7Supervise the renovation. During the work it’s important to make decisions quickly, monitor the budget and quality, and coordinate contractors.
  8. 8Check the warranty and keep the documents. Keep receipts, estimates, contracts and leftover materials; they may come in handy later.

05Types of renovation

Before looking for contractors or a designer, you need to define exactly what kind of renovation you need.

By complexity, a renovation can be cosmetic or major.

By purpose, a renovation can be for yourself, for rent or for sale.

By level, a renovation can be budget, comfort or premium.

How to assess the apartment’s condition before renovation

You need to assess the apartment’s condition before renovation to understand the real scope of work in advance. Sometimes an apartment looks fine but may have hidden problems. Such a check helps calculate the budget and timelines more honestly and avoid a situation where a cosmetic renovation suddenly turns into a major one.

The best option is to carry out an audit: call a specialist with measuring instruments and get a report on the apartment’s technical condition.

  • For new builds without finishing, they check: the evenness of walls, corners and floors, layout features (beams, columns), utility entry points, identification of load-bearing and non-load-bearing walls, the quality of the screed and plaster.
  • For resale, they add: the location and condition of old utilities (water supply, heating, underfloor heating, electrics), the quality of the electrical panel, cracks, heat loss through windows and the entrance door, and the condition of floors.

If you have concerns about seismic resistance, you can call a seismologist to assess the condition of the building; the service costs 30–40 thousand AMD.

Which elements most often need replacing

  • In new builds, partial removal of cracked plaster is most often required. In some cases the screed needs replacing if there are cracks.
  • In resale, the list depends entirely on your plans. Resale apartments are most often bought with old renovation, so everything gets demolished. If the resale apartment has a recent renovation, you may get by with repainting the walls and replacing furniture.

When electrics and plumbing need to be replaced

If your apartment has only 2–3 circuit breakers in the panel, then with 99% probability all the electrics need to be redone, otherwise there is a risk of wires overheating and a fire.

When a major renovation is needed

  • If it’s a new build, a major renovation is the default.
  • If it’s resale: a pipe leaks, a breaker catches fire, there is mold throughout the building, or you constantly keep fixing and replacing things.

Which works require approval

  • Demolition of load-bearing structures (Yerevan Municipality).
  • Moving gas pipes and the boiler (agree with Gazprom).
  • Installing air conditioners (agree with the management company).

06The first step: creating a project with a designer

A renovation usually starts not with builders, but with a designer.

  1. 1A good designer first helps you figure out styles, shows different approaches to the interior, and finds out your habits, lifestyle and the scenarios of using the apartment. For example: where you have breakfast, how you host guests, whether you need a desk, how much storage you’ll need, how you spend evenings at home.
  2. 2After that the designer makes the first sketches and layout solutions.
  3. 3Then comes the most important part, the technical design project. It later becomes the main instruction for the builders. In essence, it is a set of drawings from which the builders understand exactly what needs to be done.
  4. 4After the drawings are prepared, you and the designer go through the entire project again, discuss details and make corrections.
  5. 5Only after that does the second part of the designer’s work begin, the visualization (rendering). The designer creates images of the future apartment so you can see how the interior will look in real life before the renovation starts. In parallel, you start choosing everything that will surround you every day: materials, colors, tiles, wallpaper, switches, plumbing, light fixtures, furniture and decor.
  6. 6Usually the designer helps with the selection and accompanies you to shops and marketplaces.
  7. 7When the visualizations and drawings are ready, you receive a complete design project.

Why a design project is not a waste of money

Many people think you can simply “explain to the builders verbally” how the apartment should look and not spend money on design. In practice this almost always leads to problems.

The simplest example is moving a socket. At the design stage, changing its position costs nothing. But if you decide to move it during the renovation, consequences begin:

  • work has to be stopped;
  • the crew sits idle and may take another job in the meantime;
  • the scope of work and materials have to be recalculated;
  • negotiations about extra payments begin, and you pay for the rework.

And this applies not only to sockets, but literally to the whole renovation.

So a design project is better seen not as “pretty pictures” but as a detailed instruction for builders. When there is a project, the relationship between you and the contractor becomes much clearer and calmer.

When a design project is needed: it is basically needed by default. For example, if the property is an old building without renovation, a new build without finishing, or an apartment with a complex layout change.

When you can do without: a cosmetic renovation, a renovation of a simple apartment for rent, or if you already have a lot of experience.

What a design project usually includes: measurements of the premises, layout, a technical project (drawings for workers), visualization (2D/3D), and materials lists.

We cover designer prices in the “Renovation budget” section, where we also calculate the renovation budget.

07Implementing the project: choosing who does the work

Once the project is ready, you decide how it will be carried out.

There are six basic renovation strategies:

  1. 1Do it yourself
  2. 2A handy friend
  3. 3An all-round craftsman
  4. 4You are the foreman
  5. 5A private crew
  6. 6A renovation company

This is not about “cheaper or more expensive”. It’s about balancing three things: money / time / nerves, with quality as their derivative. Each format is a different combination of these three and a different level of your involvement.

Below we look at each of them in detail, with pros and cons.

How to choose a contractor before the renovation starts

On Yerevan’s growing renovation market, the main risk is not failing to find a contractor but choosing a weak one. Good specialists are overloaded, while weak ones are always “free and ready to start tomorrow”. So vetting a contractor is not a formality but a critical stage that directly affects the budget, timelines and your nerves.

08The renovation estimate

Once you have a design project and a chosen renovation strategy (do it yourself, a handy friend, an all-round craftsman, you are the foreman, a private crew, a renovation company), the next important step is to order an estimate. It should be made not by the designer or a craftsman “by eye”, but by an estimator. You can hire one separately, or they may be part of a renovation company.

Why it matters: from the same design project you can get an estimate of either 20 or 70 types of work. And this isn’t just a difference in detail: the final budget, timelines and the number of “surprises” during the renovation depend on it directly.

A good estimator doesn’t just count meters and multiply them by the cost of work. They check the project for realism:

  • which works are really needed;
  • which materials are available on the market;
  • which technologies must be followed;
  • where additional costs may arise.

If the estimator works inside a renovation company, they usually cross-check the estimate with the contractors, the designer and the technical director. Such an estimate ends up much closer to reality. With proper preparation, the margin of error can be around 5%.

An estimate made “by eye”, with words like “around”, “approximately” and “plus or minus”, can easily grow one and a half to two times in the end. So the more detailed the estimate at the start, the fewer conflicts and sudden extra payments later.

A properly made estimate gives you not only a list of works but also a list of the necessary materials. This helps you:

  • understand the overall budget in advance;
  • avoid unnecessary purchases;
  • not overpay for things you don’t actually need.

You need to read the estimate. Some companies may include works that don’t actually exist in your property, or, conversely, omit some mandatory stages to make the offer look cheaper. So at the very least go through the estimate line by line, and better yet, ask all your questions before signing the contract.

An example of a finished detailed estimate:

09The contract with the contractor

Once the project is ready and you have talked to several contractors and received their estimates, you can choose who does the work and move on to the contract.

The contract is not a formality but the main document you will come back to if something goes wrong during the renovation. If the contract is poorly written, almost all disputed situations will later be resolved not in your favor.

So it’s important to record in it not only the total cost but also the rules of the game: what exactly the contractor does, for how much money, by when, and on what scheme you pay.

What must definitely be recorded:

Cost of work

The contract must state the exact cost of the work or a clear calculation mechanism. This is needed so that you understand your budget in advance and the contractor cannot raise the price endlessly during the renovation. If the cost can change, that must also be spelled out: in which cases, for what reason and exactly how it is agreed. Wording like “approximately”, “we’ll calculate later” and “we’ll figure it out as we go” is better removed before signing.

Scope of work

The contract needs to specify in detail which works are performed, what is included in the price and by what technology everything is done. It is especially important to record the technology of the work, since this is where conflicts and misunderstandings most often begin. For example, you can agree to “do the walls”, but for the client it will mean one result and for the craftsman a completely different set of actions. So the more precisely the scope of work is described, the clearer it is what exactly you get for your money.

Timelines

The contract must state the completion date of the renovation. It’s best not just to write an approximate date but to define in advance what counts as a delay, who bears responsibility for it and what penalties apply. The logic is usually this: if the delay is the contractor’s fault, they pay a penalty. If it’s the client’s fault, for example materials didn’t arrive on time or decisions take too long, the crew’s idle time may be paid for. It’s an unpleasant clause, but it’s better to discuss it at the start than to argue during the renovation.

Payment stages

A renovation is usually divided into 3–4 stages. The right scheme looks like this: you pay an advance for the first stage, the contractor performs the work, you accept the result, and only then is the next stage paid. Don’t pay for the entire renovation in advance. Staged payment reduces risks for both sides: the contractor has money to start the work, and the client keeps control over the process.

10Renovation budget

The renovation budget consists of:

  • the cost of the design project (technical drawings and visualizations);
  • renovation works, rough and finishing materials;
  • furniture, appliances and delivery costs;
  • a reserve of 10–20% for unforeseen expenses.

More detail on each item below.

Cost of the design project

It is usually calculated per square meter. The price depends on the designer’s level, the project’s composition, the detail of the drawings, the presence of visualizations and supervision. On average you can use these ranges as a guide:

  • Budget: up to 10,000 AMD per sq. m.
  • Comfort: 12,000 – 15,000 AMD per sq. m.
  • Premium: 20,000 to 40,000 AMD per sq. m.

Cost of renovation works

In Armenia it can differ greatly depending on the property, the level of renovation and the contractor. On average across the market you can use these ranges as a guide:

  • Budget: 40,000 – 60,000 AMD per sq. m.
  • Comfort: 70,000 – 100,000 AMD per sq. m.
  • Premium: 120,000 – 150,000 AMD per sq. m.

Cost of rough and finishing materials

Rough materials usually come to about 45,000–50,000 AMD per sq. m. This includes mixes, cables, pipes, fasteners, primers and other materials that aren’t visible once the renovation is finished but form its base.

The cost of finishing materials is harder to calculate. It depends on your preferences, the design level and the chosen brands: tiles, plumbing, lighting, flooring, doors, wallpaper and other solutions. For calculations you can use a cost starting from 40,000 AMD per sq. m.

Cost of furniture, appliances and delivery

Very roughly you can allow around 40,000 AMD per sq. m, but the spread here is also large: a built-in kitchen, wardrobes, fittings and appliances can noticeably change the final sum.

11Purchasing materials

It’s better to plan the purchase of materials before the renovation begins. Otherwise the site will keep stopping: first there isn’t enough adhesive, then the tile arrives late, then the needed installation frame is out of stock.

If you renovate on your own, you buy the materials yourself too. Most often at construction markets, hypermarkets or specialized stores. In this format it’s important to make a list in advance and understand the order of work, so you don’t buy extra and don’t forget what the craftsmen can’t move on without.

If you work with private contractors or a crew, it’s better to ask them for a list of materials for each stage. Then you can buy everything yourself and arrange delivery to the site. This gives more control over the budget but requires your time and involvement.

If you work with a renovation company, the company most often buys the rough materials itself. And usually it really is better to hand this process over to them: they understand which materials are needed for a specific technology, where to get them and in what quantity. Plus, companies often have special terms with suppliers, and sometimes buying through them is cheaper than buying directly.

Finishing materials (tiles, plumbing, wallpaper, lighting, flooring, furniture and appliances) are usually chosen by you. The purchase itself you can keep for yourself or delegate to the foreman, the crew or the renovation company. It’s important to agree in advance who is responsible for what: who chooses, who pays, who checks availability, who organizes delivery and who accepts the material on site.

Ways to pay for purchases

There are two most common options.

First: you give a deposit to the crew or renovation company. They buy everything needed in stages, and at the end give you a report with receipts and delivery notes.

Second: you ask for a list of materials for a specific stage, buy and deliver everything yourself, and leave the contractors a small budget to top up consumables: screws, primer, a bag of mix or other small things that almost always come up along the way.

How to save on materials

Saving is a separate question. You can save on materials, but it’s important not to save on quality and shelf life. Especially with mixes: tile adhesive, plaster, putty and other bagged materials. They must be fresh and properly stored. An expired or damp mix can later cost much more than the savings.

There are several ways to save.

  • Choose a slightly cheaper material without a critical loss in quality.
  • Optimize the purchase itself: find a supplier, an importer you know, a seller with a good discount, or buy through the renovation company if it has better terms.
  • This works more often with finishing materials and interior items: wallpaper, light fixtures, decor and some furniture can be ordered as analogues on marketplaces from China, Russia or other countries.

What is important to order in advance

Some materials can’t be left “for later”; they need to be bought or ordered in advance so the renovation doesn’t suddenly stop.

First of all, this is everything built into walls or affecting dimensions: the bathtub, the toilet installation frame, built-in mixers, made-to-order tiles, designer wallpaper, imported built-in appliances, plumbing, the kitchen, wardrobes and other cabinet furniture.

Built-in cabinet furniture is usually ordered closer to the end of painting work, when exact measurements can be taken. But it’s better to choose the contractor, materials, fittings and approximate configuration earlier; otherwise after the renovation you’ll have finished walls and several more months of waiting for the kitchen or wardrobes.

12The process of renovation works

Renovation works have a sequence. It may change slightly depending on the property, but the general principle is this: first remove what’s unneeded, then build the new, then run the utilities, close them up with rough work, and only after that move to finishing.

  1. 1Demolition. First everything unnecessary is removed from the apartment: old partitions, tiles, floors, doors, plumbing, old finishes and everything that shouldn’t remain in the new renovation. IMPORTANT: don’t demolish what shouldn’t be demolished: load-bearing walls, ventilation shafts and utility risers.
  2. 2Building new partitions and structures. After demolition, everything that changes the future layout is built: new walls, partitions, frames for installations. Walls are plastered with gypsum plaster in rooms and cement plaster in bathrooms.
  3. 3Engineering and utilities. At this stage walls are chased, wires and pipes are laid, and hidden elements are installed: installation frames, built-in mixers, outlets for appliances, plumbing, lighting and equipment. Everything built into walls must be thought out in advance. After rough and finishing works, redoing such things is expensive and unpleasant.
  4. 4Rough leveling. The floor screed is made and the bases for future finishing are leveled. The better the rough base is made, the neater the tile, paint, wallpaper and flooring will later lie.
  5. 5Finishing. Laying tiles, painting, wallpaper, installing flooring, skirting boards and other finishing elements. The apartment starts to look “ready”.
  6. 6Final installation. At the end, doors, plumbing, light fixtures, sockets and switches, the kitchen, furniture, appliances and decor are installed. It starts to feel like a finished renovation.

All the construction and renovation work is done by the contractor. But this doesn’t mean the client drops out of the process entirely.

The client’s areas of responsibility

Even with a good crew or renovation company, the client usually keeps several important areas of responsibility.

1. Purchasing and delivering materials

If materials don’t arrive on time, the site stops. And a stopped site almost always means lost time and money: the crew waits, timelines shift, and some of the work has to be moved.

So large and expensive materials are better planned in advance together with the contractor. This especially applies to everything that affects the technology and sequence of work: plumbing, tiles, installation frames, built-in mixers, doors, engineering elements.

Small consumables are usually easier. You can leave a small deposit to top up missing materials, or fully delegate purchasing to the construction company, but always with reporting by receipts, delivery notes or reconciliation statements.

2. Making decisions quickly

During a renovation, questions constantly arise that can’t be fully anticipated at the start: which paint shade to choose, exactly how to lay the tile, which mixer to install, which profile, fittings or technical solution to use.

A construction site has its own pace. If the client thinks for a long time, doesn’t answer messages or leaves important decisions “for later”, timelines start to slip. So it’s better to prepare options in advance, keep references at hand and agree on decisions quickly. This doesn’t mean making everything in a rush, but it’s important to understand that some questions on a site can’t be put on pause without consequences.

3. Financing the renovation

Before work starts it’s important to calculate not only the cost of the crew itself but the whole budget: works, rough materials, finishing materials, delivery, carrying up, furniture, appliances and small expenses that almost always appear along the way.

A renovation often costs more than initially expected. So it’s better to build in a financial reserve in advance and spread payments across stages: advance, performance of work, acceptance of the stage, next payment.

4. Control and acceptance of work

Even if you hired a good crew, the quality of work still needs checking. You can do it yourself if you understand the basic technology, or through technical supervision or specialized professionals.

Control isn’t about “breathing down their necks” but about noticing mistakes in time. The earlier a mistake is found, the cheaper and simpler it is to fix.

5. Coordinating third-party contractors

During a renovation you almost always have to deal with more than just the crew. In parallel the management company, the internet provider, the gas service, window installers, furniture makers, and those who measure the kitchen, appliances, doors and other elements come into play.

It’s important to organize measurements on time, order equipment, agree arrival dates and make sure different contractors don’t get in each other’s way on site. This task can also be delegated to the renovation company. That’s the point of the “turnkey” format: you don’t become the site dispatcher, but get a single center of responsibility that runs the process, coordinates people and takes most organizational questions off you.

13After the renovation: what to do right away

When the renovation is finished and the apartment is handed over, work with the property doesn’t end there. There are a few things best done right away, while all the documents, contacts and details are still at hand.

Clarify the warranty

Be sure to record the warranty period for the work with the contractor and clarify exactly what it covers. This is especially important for plumbing, electrics, engineering systems and hidden works, that is, everything that is hard to check later or quickly redo without opening up the finishes. It’s also worth discussing separately in which cases the warranty doesn’t apply. For example, if you interfered with the system yourself, called an outside craftsman or violated the operating rules. The clearer this is written at the start, the fewer disputes later.

Keep the documents

Don’t throw away the contract, estimates, receipts, completion certificates, delivery notes and the contacts of contractors and suppliers. At first glance it seems they’re no longer needed after the renovation, but in practice these documents may be needed many more times. They’ll come in handy for warranty cases, for a future renovation, when selling the apartment, or if in a year you need to buy more material, replace a light fixture, find the same paint shade or figure out who exactly did a particular section of work.

Keep a reserve of materials

After the renovation, be sure to keep a small reserve of finishing materials: a few tiles, leftover laminate, paint, grout, wallpaper, skirting boards, fittings and other elements that may be needed for minor repairs. Even with careful use, chips, scratches, leaks and marks from furniture or appliances appear over time. And the problem is that after a few years it can be hard, and sometimes impossible, to find exactly the same tile, paint or laminate.

14Conclusion

The main idea of this guide: a good renovation starts not with buying materials or looking for craftsmen, but with preparation. The clearer your goal, project, estimate, agreements and order of action, the less chance the renovation turns into an endless construction site with rework, conflicts and sudden expenses.

In Armenia this is especially important. Many apartments are sold in shell condition, strong specialists are often busy, there are few common quality standards on the market, and a significant part of agreements is still built on personal recommendations and words. So preparation here isn’t bureaucracy, it’s your protection.

Let this guide be not a strict instruction for every situation but a reference map. With it, it’s easier to ask the right questions, compare contractors, read estimates, make decisions and understand where you can save and where saving will later cost more.

Thank you for reading this guide to the end! If you think something should be added, or you want to ask for help, you can write to:

With us you can:

  • get the contacts of a proven, reliable full-cycle construction crew (we bring them in on our projects and our clients’ projects);
  • order a renovation management service (our specialist takes on the whole load of organizing processes, vetting contractors and supervision; more about the service here: https://t.me/sqm_am/195);
  • order an engineer’s inspection of an apartment or house before purchase (a specialist’s audit gives a clear picture of the apartment’s condition).

That’s all. We hope it was useful and that this guide helps you go through your renovation a little more calmly.